Project Name Water and Wastewater Services Expansion Project in Manaus
Country The Federative Republic of Brazil
Area of Operation  Water & Sanitation
Concept Approval Date 8 Oct 2021
Board Approval Date 13 December 2022
Total Project Cost USD 356 million
Initial Limit of NDB Financing USD 80 million
Current Limit of NDB Financing USD 80 million
Borrower Manaus Ambiental S.A., a fully owned subsidiary of AEGEA Group
Project Context
Manaus is a growing industrial city in the north-western state of Amazonas in Brazil. While access to water infrastructure is available to 98 per cent of the city’s residents, access to wastewater infrastructure is rather low and available only to 26 per cent of the population. The existing infrastructure has not kept pace with the recent accelerated urban growth in the city, especially in the areas occupied by the poorest segments of the population, and requires significant investments in its modernization and expansion.
Project Objective

The Project aims at rehabilitating or developing water and wastewater infrastructure in Manaus to guarantee access to reliable and affordable water and wastewater services for the population; improving public health and reducing water-borne diseases; and ensuring compliance with environmental standards.

Project Description

The Project comprises the following components:

  • Expansion and improvements in the water infrastructure;
  • Expansion and improvements in the wastewater infrastructure;
  • Loss reduction; and
  • Operational efficiency, security, and other investments.

 

Expected Benefits

The key benefits of the Project include: (i) improved quality of water services for the citizens with a greater number of households connected to the water network; (ii) reduction of untreated effluent or improved quality of wastewater discharged into the Amazon River basin; and (iii) improved condition and quality of underground water and soil by connecting more households to the sewage network.

Environmental and Social Aspect

The Project has been categorized as Category B in line with the NDB’s Environment and Social Framework, with an environmental and social risk tier of B-2 ‘Medium Risk’. Main E&S impacts will be addressed and mitigated by implementing relevant E&S management plans as per the country system, the Borrower’s Environmental and Social Management Systems, and additional measures for the Project agreed with NDB and reflected in the Environmental and Social Impact Management Plan.

Financing Aspect
Source of Fund Amount (USD million)
New Development Bank
80
Other sources
276
Implementation

The implementation period of the Project is 2022-2027

Contacts NDB Borrower Implementation Agency
Private Sector and Non-Sovereign Guaranteed Transactions Department:

Akhil Kumar

 

Americas Regional Office:

Mauricio Xavier

Manaus Ambiental S.A.
 
Gabriel Bertolazzi, Financial Operations

gabriel.bertolazzi@aegea.com.br

Manaus Ambiental S.A.
 
Gabriel Bertolazzi, Financial Operations

gabriel.bertolazzi@aegea.com.br